Point au 27/11/2015Status of contruction work in our Cần Giuộc Orphanage – To help ushttps://lesenfantsdudragon.com/nous-aider/don/

26/11/2015 : Steps of main stairs and flooring should all be ready by tonight. (90% on the picture) as well as inclusion of main betworks in the slab (60% to date).
Casting is scheduled for next week.

25/11/2015 : In term of flooring for 3rd floor, only finishing and siding remains ( progress is 85%).
Ree bars is going fast, stairs are finished>