01 au 10/12/2015 : Blindage, strengtening shorting, casting cement and colums in 3rd floor.
02 au 08/12 : Pouring sand in ground floor.
04 au 11/12 : Installing fresh water d drainage system in ground floor.
12 au 05/01/2016 : Blindage and iron structure for roof hopers.
06/01 : Pooring cement, polishing of roof hopers.
06 au 10/01 : Blindage, strengtening shorting, casting cement for roof structure
07 au 31/01 : Blindage and stell meshing.
31/01 : Pooring cement in roof strcture.
11 au 30/01 : Building walls for ground floor…