15/06/2015 : Live from construction site, Thanks for sharing and don;t forget we are still actively looking for sponsors and donators. Feel free to contact us may you need any supporting documents https://lesenfantsdudragon.com/nous-aider/ -> Schedule and technical details? 14 casting of undeground poles per day, equivalent to 280 poles to be casted on 3.5 weeks. The phase of inserting the poles in the ground will start on beginning of July (21 days are necesary for proper drying before to use).

Les travaux de construction de l'orphelinat